twitterlinkedinfacebookemailaddarrow-downarrow-outlinearrow-outline-downarrow-outline-leftarrow-outline-uparrow-upclosedownloadformat-pdfhelpinfoinfo-outlinelink-external-outlinemenusearchsource-handshakesource-klsource-web

Belize

PPP Framework

Agencies

No dedicated PPP Unit.

Laws and policies

No dedicated PPP Law.

PPP Projects in Infrastructure

Read more about the methodology and the data source
Project Name Sector Financial Closure Year Investment ($US Million)
Belize Electricity Limited Electricity 1992 $199.10
Macal/Mollejon Hydroelectric Electricity 1995 $143.00
Belize Co-generation Energy Limited Electricity 2007 $62.00
Belize Water Services Water and sewerage 2001 $49.60
International Telecommunications Limited ICT 2003 $45.00
Belize City Port Ports 2002 $37.60
Caye Caulker to Ambergris Caye submarine cable ICT 2019 $8.60
Project Name Sector Financial Closure Year Investment ($US Million)
Caye Caulker to Ambergris Caye submarine cable ICT 2019 $8.60
Belize Co-generation Energy Limited Electricity 2007 $62.00
International Telecommunications Limited ICT 2003 $45.00
Belize City Port Ports 2002 $37.60
Belize Water Services Water and sewerage 2001 $49.60
Macal/Mollejon Hydroelectric Electricity 1995 $143.00
Belize Electricity Limited Electricity 1992 $199.10
Project Name Sector Financial Closure Year Investment ($US Million)
Macal/Mollejon Hydroelectric Electricity 1995 $143.00
Belize Co-generation Energy Limited Electricity 2007 $62.00
Belize City Port Ports 2002 $37.60
Caye Caulker to Ambergris Caye submarine cable ICT 2019 $8.60
Project Name Sector Financial Closure Year Investment ($US Million)
Caye Caulker to Ambergris Caye submarine cable ICT 2019 $8.60
Belize Co-generation Energy Limited Electricity 2007 $62.00
Belize City Port Ports 2002 $37.60
Macal/Mollejon Hydroelectric Electricity 1995 $143.00

Infrastructure Indicators

Read more at World Bank Data

GCI Infrastructure Score

The Global Competitiveness Index (GCI)  is published in the Global Competitiveness Report and assesses the competitiveness landscape of 140 economies. The GCI Infrastructure Score is a component of the overall index and covers transport, electricity and telephony infrastructure. 

Read more at WEF

N/A

GCI Score as of 2019

Resources

    • 2014
    • PPIAF, World Bank
    • PPIAF, World Bank Group (WBG)

    Caribbean Infrastructure PPP Roadmap

    Experience with PPPs to date in the Caribbean has been mixed. PPPs are not new in the region, having been used to deliver new or improved roads, ports, airports, bulk water treatment facilities, and electricity generation plants. Many PPP projects have operated successfully for years, delivering high-quality infrastructure facilities. Others have faced challenges. In many cases, the complexity of the PPP development and implementation process has meant long delays in delivering projects; others resulted in questionable value or unexpected costs to governments or consumers. This raises a question: How can Caribbean governments successfully navigate the challenges to make the best use of PPPs to deliver improved infrastructure assets and...

Date last reviewed: February 16, 2016